Island's Expressway Improvements
|
Design
|
$2,078,567
|
$-
|
On Going
|
Roads
|
2014-2020
|
Project will make operational and safety improvements on Island's Expressway between the Wilmington River the Richardson Creek (Oatland Island). Project will involve milling, resurfacing, turn lane and access improvements as well as drainage improvements.
|
Project design is complete.
|
|
Johnny Mercer at Walthour Intersection Improvements
|
Design
|
$500,000
|
$-
|
TBD
|
Roads
|
2014-2020
|
Project intersection improvements at Johnny Mercer and Walthour.
|
Public Information Open House held March 28, 2022.
|
A Public Information open house was held and intersection design options were presented to the community. The roundabout intersection was favored by the comments received during the comment period. Surveying is now completed within the project area. Preliminary Engineering Design is underway and is to be completed first quarter 2024.
|
Benton Boulevard Extension
|
Construction
|
$11,000,000
|
|
|
Roads
|
2003-2008
|
To construct road from Jimmy DeLoach Parkway to Highway 30.
|
|
Project was to tie into Effingham Parkway. Terminus of the Parkway has not been established. No intergovernmental agreement with the GDOT.
|
Benton Boulevard Extension
|
Construction
|
$2,000,000
|
|
|
Roads
|
2014-2020
|
To construct road from Jimmy DeLoach Parkway to Highway 30.
|
|
Project was to tie into Effingham Parkway. Terminus of the Parkway has not been established. No intergovernmental agreement with the GDOT.
|
TSM on Skidaway Dr. from Ferguson Ave. to Victory Dr.
|
On Going
|
$1,091,362
|
|
|
|
1985-1993
|
Intersection improvements and the addition of a third lane for left turns. (TSM = Traffic System Management)
|
This project is currently in the design stage. $5,000,000 has been budgeted for the project.
|
|
S.R. 307/Dean Forest Rd. Extension
|
|
|
|
|
Roads
|
1998-2003
|
To extend S.R. 307 (Dean Forest Road) from S.R. 25/U.S. 17 to Veterans Parkway.
|
|
|
Libraries
|
On Going
|
$5,000,000
|
|
|
|
2014-2020
|
Construct new library
|
Pending site identification
|
|
Mother Mathilda Beasley Park
|
On Going
|
$500,000
|
|
|
Cultural
|
2014-2020
|
Construct improvements to park
|
|
|
Public Safety - CEMA Facility
|
Design
|
$20,000,000
|
|
On Going
|
Other
|
2014-2020
|
Construct Public Safety Facility for CEMA and 911 operations.
|
|
EOC to be located at Airport
|
Quacco Road at US 17 Intersection Improvements
|
Construction
|
$3,500,000
|
$500,000
|
On Going
|
Roads
|
2014-2020
|
Intersection reconstruction and widening of Quacco Road between US 17 and Winding Way. Project also includes pedestrian improvements.
|
Construction underway by Preferred Materials.
|
|
Quacco Road Improvement Project
|
Right of Way
|
$13,000,000
|
$-
|
On Going
|
Roads
|
2014-2020
|
Widen Quacco Road to a 3-Lane Section, including the addition of right turn lanes and bus turnouts between Winding Way and the existing bridge over I-95. Project also includes adding pedestrian facilties along the corridor.
|
Right of way acquisition underway by County staff.
|
|
Scott Stell Park
|
On Going
|
$750,000
|
|
|
Recreation
|
2014-2020
|
Various park and pavement improvements
|
|
|
Soccer Complex
|
On Going
|
$6,500,000
|
|
|
Recreation
|
2014-2020
|
Add additional multi-use fields, restrooms and parking
|
|
|
Tybee Island Beach and Facility Improvements
|
Complete
|
$2,850,000
|
|
|
Cultural
|
2014-2020
|
Construct restroom facilities
|
|
|
Westlake Drainage Improvements
|
Design
|
$2,000,000
|
|
|
Drainage
|
2014-2020
|
Improve culvert and channel capacity and construct new systembs to divert storm water.
|
|
|
Health Department Midtown Clinic
|
Complete
|
$2,000,000
|
|
|
Other
|
|
|
|
|
Truman Linear Park Trail, Phase 2A
|
Construction
|
$5,500,000
|
$4,000,000
|
On Going
|
Roads
|
|
New 10-ft trail from Lake Mayer to DeRenne Avenue.
|
Construction underway.
|
|
Public Safety and Fire Equipment
|
On Going
|
$400,000
|
|
|
Other
|
2008-2014
|
|
|
|
Quarterman Drive Improvements
|
Concept
|
$150,000
|
|
On Going
|
Roads
|
2008-2014
|
Project will look at repairing the road and culvert to improve long-term operation and safety of the road.
|
Need to begin design.
|
|
Roads, Streets and Bridges - County-wide
|
Various
|
$20,000,000
|
|
|
Roads
|
2008-2014
|
Allocations for these projects cut due to reduced revenue collections.
|
|
|
Unicorporated County Projects - Sidewalks
|
On Going
|
$2,000,000
|
|
|
Other
|
2008-2014
|
Starts of projects subject to future revenue collected through 9/30/2014.
|
|
|
Unincorporated County Projects - Flood Control
|
On Going
|
$8,000,000
|
|
|
Drainage
|
2008-2014
|
Starts of projects subject to future revenue collected through 9/30/2014.
|
|
|
Unincorporated County Projects - Parks and Recreation
|
On Going
|
$5,390,000
|
|
|
Recreation
|
2008-2014
|
Starts of projects subject to future revenue collected through 9/30/2014.
|
|
|
Unincorporated County Projects - Roads
|
On Going
|
$11,600,000
|
|
|
Roads
|
2008-2014
|
Allocations cut due to reduced revenue collections. Expenditures of $1.5million as of 2/27/2013.
|
|
|
Walthour Road Sidewalks
|
Design
|
$150,000
|
|
On Going
|
Roads
|
2008-2014
|
Project will look at adding a sidewalk and bank stabalization along Walthour Road in the vicinity of the bridge.
|
Preliminary design underway by Wolverton.
|
|
Weightlifting Center
|
Complete
|
$500,000
|
|
|
Cultural
|
2008-2014
|
|
|
|
Tatemville Community Center
|
Complete
|
$-
|
|
|
Cultural
|
2008-2014
|
Completed with funds previous SPLOST.
|
|
|
Westside Police Precinct
|
Complete
|
$3,500,000
|
|
|
Other
|
2008-2014
|
Construct a precinct on the westside of County.
|
|
|
Burnside Island Community Park
|
Complete
|
$69,788
|
|
|
Recreation
|
2014-2020
|
Construct playground
|
|
|
Berwick Blvd at US 17 Intersection
|
Complete
|
$480,000
|
|
|
Roads
|
2014-2020
|
To improve operational safety by constructing dual left trun lanes from Berwick Blvd onto US 17
|
|
|
Concord Road Storm Drainage Improvements
|
Complete
|
$3,050,000
|
|
05/01/2019
|
Drainage
|
2014-2020
|
Replace open channel with closed systeme and improve outfall.
|
|
|
Isle of Hope Park
|
Complete
|
$69,996
|
|
|
Recreation
|
2014-2020
|
Construct playground equipment
|
|
|
Memorial Stadium
|
Complete
|
$14,015,542
|
NA
|
12/21/2018
|
Building
|
2014-2020
|
Design and construction of new 5,000 capacity Stadium, synthetic turf field striped for football and soccer, Press Box, Officials rooms, 8ft wide recreational track, 2 story 10,900 sq ft End Zone Building that houses on the first floor Team Locker Rooms, two sets of Public Restrooms and Concessions. The 4,700 sq ft second floor accommodates a 100 person Community Center and offices for Parks and Rec. Included is a Memorial Plaza to honor the fallen soldiers of the County.
|
|
|
Police Precinct
|
Complete
|
$2,500,000
|
|
04/25/2017
|
Other
|
2014-2020
|
Construct police precinct on Whitefield Avenue
|
|
|
Charles Brooks Park
|
Design
|
$2,000,000
|
|
|
Recreation
|
2014-2020
|
Construct new ballfields and parking lot.
|
Project is designed and is in the permitting stage
|
|
Civil Rights Museum Improvements
|
On Going
|
$3,000,000
|
|
|
Cultural
|
2014-2020
|
Upgrade HVAC system and replace roof.
|
|
|
Community Centers
|
On Going
|
$2,000,000
|
|
|
Cultural
|
2014-2020
|
Construct various centers
|
A community center was constructed at Memorial Stadium
|
|
Dog Park
|
Concept
|
$500,000
|
|
|
Other
|
2014-2020
|
Construct dog park in Unincorporated Chatham County
|
|
|
Cooperative Extension
|
Design
|
$2,250,000
|
|
|
Cultural
|
2014-2020
|
Construct office space for Cooperative Extension operations and Children's Garden at Coastal Botanical Gardens.
|
|
|
Fleet Facility and vehicle Replacement
|
Construction
|
$6,500,000
|
|
|
Other
|
2014-2020
|
Construct new County Fleet Facility and replace aging vehicles
|
|
|
US 80 Sidewalks
|
Design
|
$500,000
|
$-
|
On Going
|
Roads
|
2003-2008
|
Project will consider constructing sidewalks along US 80 between Johnny Mercer Boulevard and Wilmington Village Way.
|
Survey and preliminary design underway by task order contract.
|
|
Carver Heights Community Center
|
Complete
|
$896,760
|
|
|
Cultural
|
2008-2014
|
|
|
|
Chatham Area Transit
|
Complete
|
$1,968,140
|
|
|
Cultural
|
2008-2014
|
Reimbursements to CAT for capital outlay projects are complete.
|
|
|
Cloverdale Community Center
|
Complete
|
$694,627
|
|
|
Cultural
|
2008-2014
|
|
|
|
County Administrative Buildings
|
Complete
|
$3,650,000
|
|
On Going
|
Other
|
2008-2014
|
|
|
|
County Health Department
|
Complete
|
$8,425,448
|
|
On Going
|
Other
|
2008-2014
|
Projected completion in July 2013.
|
|
|
Hutchinson Island Slip 3
|
Complete
|
$3,375,134
|
|
|
Other
|
2008-2014
|
|
|
|
Jail Facility Expansion Phase 1 - Level 1 County-wide
|
Complete
|
$80,702,318
|
|
12/19/13
|
Building
|
2008-2014
|
Detention Center expansion added 396K sq ft, 4 housing units or 852 beds, 33 additional beds in new Medical, new Intake, Transfer, Warehouse, Commissary
|
|
|
Jail Facility Expansion Phase 2 - Level 1 County-wide
|
Complete
|
$19,297,000
|
|
In Closeout
|
Building
|
2008-2014
|
Partial renovations to Unit 5, repalcement of roof, re-paving of perimeter road, Work Release Center, new K9 building
|
|
|
Judicial Courthouse Phase 1 - Tom Coleman
|
Complete
|
$24,012,909
|
NA
|
8/2018
|
Building
|
2008-2014
|
Being constructed in phases. Costs thus far include relocations of agencies from the courthouse in order to facilitate continued renovations with the courthouse.
|
|
|
Juvenile Court Complex- Level 2 County-wide
|
Complete
|
$3,370,200
|
|
On Going
|
Other
|
2008-2014
|
|
|
|
Liberty City Community Center
|
Complete
|
$797,750
|
|
|
Cultural
|
2008-2014
|
|
|
|
Marine Patrol Facility
|
Complete
|
$400,000
|
|
|
Other
|
2008-2014
|
To be constructed as part of Turners Creek Boat Ramp project.
|
|
|
AMBUC Park
|
Construction
|
$1,000,000
|
|
|
Recreation
|
2008-2014
|
|
|
|
Chevis Road Sidewalks
|
Concept
|
$500,000
|
|
On Going
|
Roads
|
2008-2014
|
Project will consider constructing sidewalks along Chevis Road.
|
|
Staff is looking for grant/outside funding opportunities to leverage SPLOST funds. Project will be costly do to required drainage improvements.
|
Diamond Causeway at Green Island/McWhorter Intersection Improvements
|
Design
|
$100,000
|
|
On Going
|
Roads
|
2008-2014
|
Project will consider operational and safety improvements at the intersection.
|
Staff working on interim improvements to add flashing beacons to advanced warning signs and stop signs. Staff also working on installing rumble strips in advance of the intersection.
|
|
Distributions to Municipalities
|
Complete
|
$140,321,667
|
|
|
Other
|
2008-2014
|
"Other Capital Outlay" provided municipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries. Distribution as of 2/27/2013.
|
|
|
Drainage/Flood Control
|
Various
|
$14,600,000
|
|
On Going
|
Drainage
|
2008-2014
|
Allocations for these projects cut due to reduced revenue collections. Construction to widen Pipemakers Canal downstream of I-95 is underway.
|
|
|
Greenspace
|
On Going
|
$1,500,000
|
|
On Going
|
Other
|
2008-2014
|
|
|
|
Grove Point Road Sidewalks
|
Design
|
$710,630
|
|
On Going
|
Roads
|
2008-2014
|
Project will construct a sidewalk on Grove Point Road between King George Bouelvard and Brandy Road.
|
|
|
Hitch Library
|
Concept
|
$500,000
|
|
|
Cultural
|
2008-2014
|
|
|
|
Judicial Courthouse Phase 2 - Trial Court Building
|
Design
|
$35,200,000
|
NA
|
|
Building
|
2008-2014
|
Design and construct a new Trial Courts building approximately 160K sq ft to house 8 Superior Courtrooms, 4 State Courtrooms and support administrative spaces.
|
Project is under design
|
|
Public Safety - CEMA Facility
|
Design
|
$2,350,000
|
|
On Going
|
Building
|
2008-2014
|
Funds used towards design for facility at Hunter; design at Airport
|
|
Originally intended to be constructed at Hunter Army Base. DHS funds also used toward design
|
Golden Isles, Sugar Tree Court
|
Complete
|
$321,000
|
$-
|
2012
|
Drainage
|
2003-2008
|
Drainage Improvements to relieve structural flooding
|
|
Community has verbalized preference for closed drainage system in lieu of ditches and swales.
|
Interchange at Jimmy DeLoach Parkway and U.S. 80
|
Complete
|
$2,000,000
|
$-
|
|
Roads
|
2003-2008
|
Construct interchange
|
Concept Report approved by GDOT. Environmental Assessment being done.
|
|
Islands Expressway Bridge at Causton Bluff
|
Complete
|
$2,000,000
|
$-
|
|
Roads
|
2003-2008
|
To construct high level bridge to replace draw bridge.
|
Concept Report pending approval by the GDOT.
|
|
Islands Police Precinct
|
Complete
|
TBD
|
NA
|
07/2008
|
Building
|
2003-2008
|
New 7K sq ft Precinct including Administrative Office, Conference road, parking
|
|
Facility was constructed on land leased from the School Board
|
Martin Luther King Boulevard Traffic Safety Improvements
|
Complete
|
$2,000,000
|
$-
|
|
Roads
|
2003-2008
|
Project by the City of Savannah
|
|
|
Open Space and Greenway Projects
|
Complete
|
$5,314,987
|
$-
|
|
Other
|
2003-2008
|
Funds allocated to all municipalities (except the City of Savannah) and the County to acquire greenspace.
|
|
|
Other Capital Outlay Projects - Chatham County
|
Complete
|
$800,000
|
$-
|
|
Other
|
2003-2008
|
For County Courthouse renovations and Tax Assessors computer system
|
|
|
Other Capital Outlay Projects - Chatham County, CASA
|
Complete
|
$98,026
|
$-
|
|
Other
|
2003-2008
|
CASA (Court Appointed Special Advocate)
|
|
|
Other Capital Outlay Projects - Chatham County, Vehicles
|
Complete
|
$4,580,000
|
$-
|
|
Other
|
2003-2008
|
Funding for purchase of County vehicles
|
|
|
Other Capital Outlay Projects - City of Savannah
|
Complete
|
$29,901,183
|
$-
|
|
Other
|
2003-2008
|
Funds to be distributed to the City of Savannah under a intergovernmental agreement for other capital projects
|
|
|
Other Capital Outlay Projects - Distributions to Municipalities
|
Complete
|
$21,913,426
|
$-
|
|
Other
|
2003-2008
|
Fund allocated to municipalities for other capital outlay under intergovernmental agreements.
|
|
$2,700,000 to Bloomingdale. $3,779,500 to Garden City. $3,779,500 to Pooler. $2,254,426 to Port Wentworth. $2,600,000 to Thunderbolt. $6,400,000 to Tybee Island. $400,000 to Vernonberg.
|
Other Capital Outlay Projects - Library
|
Complete
|
$16,000,000
|
$-
|
|
Cultural
|
2003-2008
|
Funding to be distributed to the Live Oak Public Library for construction of new facilities.
|
Construction of the new library branch at Savannah Mall is underway.
|
|
Other Capital Outlay Projects - Public Safety
|
Complete
|
$17,300,000
|
$-
|
|
Other
|
2003-2008
|
Allocate funds to fire departments for capital projects, for the County/City Police Merger and for the County Courthouse
|
|
|
Other Capital Outlay Projects - Recreational, Cultural & Historic
|
Complete
|
$11,068,743
|
$-
|
|
Other
|
2003-2008
|
Allocate funds for recreational, cultural or historic preservation projects.
|
See comments for status of individual projects.
|
$1,700,000 for Tom Triplett Park, Pooler. Construction of pavilion and bridge complete. $400,000 for Runaway Park, Savannah. Construction of amenities complete. $1,900,000 for Mother Beasley Park, Savannah. Beautification phase complete. $700,000 for Boat Ramps, County. Paving of Skidaway Narrows Boat Ramp parking complete. $490,128 for Telfair Museum. Funds distributed. $1,078,283 for Fort Jackson. Funds distributed. $49,013 for W. Chatham YMCA. Funds distributed. $100,000 for Bikeway/Sidewalk Projects - McCorkle Trail. Trail along Cromwell Road under design. $1,328,248 for Civil Rights Museum. Expansion under construction. $735,193 for Tatemville Community Center. None. $68,618 for Coastal Soccer. Addition of sprinkler system and field lighting complete. $980,257 for King-Tisdell. Funds distributed. $980,257 for W.W. Law Center. On hold. $68,618 for Yamacraw Arts. Funds distributed to City of Savannah. $490,128 for Con Ed. Funds distributed.
|
Other Capital Outlay Projects - Unincorporated Chatham County
|
Construction
|
$9,411,357
|
$-
|
|
Other
|
2003-2008
|
Allocate funds for various projects in the Unincorporated County. Funds distributed to non-profits are via agreements with each agency.
|
|
$250,000 for King George Sidewalks. $75,000 for US 80 Sidewalks. $75,000 for US 80 Beautification. $100,000 for Wild Heron Sidewalks. $450,000 for Whitemarsh Island Bikeways. $950,000 for Charlie Brooks Park. $1,000,000 for Public Works Building. $1,470,385 for Greenbriar. $980,257 for Hospice. $808,712 for CAT. $117,631 for CAT Shelters. $98,026 for Rape Crisis. $1,764,462 for Royce. $144,588 for Humane Society. $784,206 for Food Bank. $98.026 for Savannah Symphony. $245,064 for Ash Tree.
|
Pipemakers Canal Widening Project, Phase 2, Section 2
|
Complete
|
$8,500,000
|
$-
|
2014
|
Drainage
|
2003-2008
|
Design and construct storm water drainage improvements and provide access for maintenance upstream of SR 307 through I95.
|
|
Project extends from west of SR307 to west end of Savannah/Hilton Head Intn`l. Airport. Features include widening of the canal and other improvements to facilitate better flow of storm water.
|
Quacco Canal Drainage Extension
|
Complete
|
$1,000,000
|
$-
|
2011
|
Drainage
|
2003-2008
|
Extend Quacco Road Drainage System from Quacco Trail to Willow Lakes Subdivision
|
|
|
Skidaway Road
|
Design
|
$2,500,000
|
|
|
Roads
|
2003-2008
|
Traffic safety improvements
|
|
|
S.R. 307 Extension from U.S. 17 to Veterans Parkway
|
Cancelled
|
$2,000,000
|
$-
|
|
Roads
|
2003-2008
|
Construct new road
|
Not feasible
|
|
S.R. 307 Widening from I-16 to U.S. 17
|
Complete
|
$2,000,000
|
$-
|
|
Roads
|
2003-2008
|
Widen road from 2 to 4 lanes.
|
Estimated completion November 2013.
|
Concept Report pending approval by the GDOT
|
Storm Drainage - County
|
Complete
|
$300,000
|
$-
|
|
Drainage
|
2003-2008
|
Funds for small capital drainage improvements
|
|
|
Truman Pkwy., Phase 5 (Sales Tax 4)
|
Complete
|
$5,000,000
|
$-
|
|
Roads
|
2003-2008
|
Construct 4-lane limited access road from Whitefield Avenue to Abercorn Extension.
|
Right-of-way acquisition to be complete by August 2008. Clearing of obstructions is in progress.
|
Construction programmed for FY 2010.
|
Unincorporated Drainage
|
Various
|
$11,000,000
|
$-
|
|
Drainage
|
2003-2008
|
Improve stormwater capacity of system (canals and structures) within the County.
|
|
|
Unincorporated Roads
|
Various
|
$14,000,000
|
$-
|
|
Roads
|
2003-2008
|
Pave various dirt roads and construct intersection improvements within Unincorporated Chatham County.
|
|
|
Telfair: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$833,000
|
$-
|
09/16/2003
|
Cultural
|
1998-2003
|
Capital outlay for Jepson Center for the Arts (Telfair Square).
|
"Complete" means Chatham County issued payments to Telfair in accordance with the agreement.
|
In conformance with the SPLOST resolution, by contract Chatham County distributed funds to Telfair for the Jepson Center project, which serves a public benefit. The Jepson Center`s cost exceeds $20+ million.
|
Thunderbolt: "Other Capital Outlay" (1998)
|
Complete
|
$458,703
|
$-
|
09/16/2003
|
Other
|
1998-2003
|
"Other Capital Outlay" provided muncipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
Complete means County issued check. City of Thunderbolt assumed responsibility by contract to expend funds in accordance with state law.
|
Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
Trade Center: Change Order 20--from Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$1,520,000
|
|
12/10/2002
|
Other
|
1998-2003
|
"Other Capital Outlay" funded city and county projects (also distributed to cities for city projects). Although the County distributed most of the funds for non-profit organization projects, some funds were designated for County projects.
|
|
Change Order 20 funded settlement of Construction Manager's claim for added costs beyond contract amount to complete construction per design documents and delays.
|
Triplett Park & S&O Canal - Greenway
|
Complete
|
$429,987
|
$-
|
|
Recreation
|
1998-2003
|
Project links the S&O Canal trail with trailhead improvements at Tom Triplett Community Park. Projects includes pavilion, restrooms and extension of sewer to SPA Park.
|
Completed: pavilion, sewer extension, restrooms. Pending:
|
Funding includes $200,000 Transportation Enhancement grant from Georgia Department of Transportation.
|
Truman Pkwy., Phase 5 (Sales Tax 3)
|
Complete
|
$-
|
$-
|
|
Roads
|
1998-2003
|
Extension of the Harry S. Truman Parkway (four lane divided limited access road) from Whitefield Ave. to Abercorn St. Includes bridge over the Vernon River and at-grade intersections at Abercorn St.
|
|
|
Tybee Island--"Other Capital Outlay" (1998)
|
Complete
|
$696,428
|
$-
|
09/16/2003
|
Other
|
1998-2003
|
"Other Capital Outlay" provided muncipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
Complete means County issued check. City of Tybee Island assumed responsibility by contract to expend funds in accordance with state law.
|
By resolution and intergovernmental in accordance with state law, Chatham County provided funds for municipal eligible projects. Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
Tybee Lighthouse: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$297,500
|
$-
|
09/16/2003
|
Cultural
|
1998-2003
|
Provide funding toward renovation of historic lighthouse and caretaker house (Tybee Island).
|
|
Funds provided through contract to non-profit organization that managed project.
|
Tybee Marine Science Center: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$50,000
|
|
09/16/2003
|
Cultural
|
1998-2003
|
Provide funding toward capital project to renovate and expand Tybee Marine Science Center. (Tybee Island)
|
|
Funds provided through contract to non-profit organization that managed project.
|
Village Green Drainage - Phase 1
|
Complete
|
$-
|
$-
|
10/31/1999
|
Drainage
|
1998-2003
|
Storm water drainage improvements. Upgrade culvert under Cambridge Drive.
|
|
|
Village Green Drainage - Phase 2
|
Complete
|
$245,000
|
$-
|
|
Drainage
|
1998-2003
|
Storm water drainage improvements and provide access for maintenance from Wimbledon Dr to SR 204.
|
|
|
Walthour Surrey Drainage - Phase 1
|
Complete
|
$80,000
|
$-
|
01/01/1999
|
Drainage
|
1998-2003
|
Storm water drainage improvements from Walthour Road to outfall at river.
|
|
|
Walthour Surrey Drainage - Phase 2
|
Complete
|
$140,000
|
$-
|
2004
|
Drainage
|
1998-2003
|
Storm water and collector system pipeing drainage improvements from Pickwick across Winchester and Lancaster to Walthour Road. Features include widening of the canal and increasing the size of culvert crossings at roadways.
|
|
|
Westlake Drainage Improvements, Phase 1
|
Complete
|
$1,809,000
|
$-
|
03/04/2002
|
Drainage
|
1998-2003
|
Storm water drainage improvements and access for maintenance. Project included doubling the size of the box culverts under Perimeter Rd on HAAF, widening the S. Springfield Canal and constructing a new bridge over the canal.
|
|
|
Westlake Drainage Improvements, Phase 2
|
Complete
|
$2,200,000
|
$-
|
2010
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements and provide access for maintenance from Oriole Drive to end of Blue Jay Avenue.
|
|
Project includes acquisition of property and relocation of residents out of flood prone area. Part of project funded with FEMA Hazard Mitigation Grant (over $600,000).
|
Westlake Drainage Improvements, RR Undercrossing
|
Complete
|
$1,500,000
|
$-
|
2009
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements and provide access for maintenance from north to south side of railroad embankment. Features include replacing two 36 inch pipes with a new single 12 foot pipe under the railroad.
|
|
|
Wilmington Park Canal - Manchester - Clarendon
|
Complete
|
$170,000
|
$-
|
12/12/2000
|
Drainage
|
1998-2003
|
Design and construction of storm water piping improvements along Clarendon from Wynngate to the golf course, and from Clarendon to Manchester. Features include some canal widening.
|
|
|
Wilmington Park Drainage - Phase 1
|
Complete
|
$1,165,000
|
$-
|
09/02/2002
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements from east to west side of Wilmington Island Road. Project features include replacing a 48" pipe with a triple 10' x 5' Box Culvert and new tide gates.
|
|
|
Wilmington Park Drainage - Phase 2
|
Complete
|
$1,000,000
|
$-
|
2013
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements and provide access for maintenance from Wilmington Island Road to North Cromwell Road. Project features include canal widening and culvert upgrades.
|
|
|
Acquisition of Henderson Golf & Mighty 8th Air Force
|
Complete
|
$16,719,000
|
$-
|
|
Other
|
2003-2008
|
Debt retirement
|
|
|
Berwick Blvd at US 17 Intersection
|
Complete
|
$480,000
|
|
|
Roads
|
2003-2008
|
To improve operational safety by constructing dual left trun lanes from Berwick Blvd onto US 17
|
|
|
City of Savannah Drainage
|
Complete
|
$51,150,000
|
$-
|
|
Drainage
|
2003-2008
|
Funds allocated by Intergovernmental Agreement to Savannah for drainage projects
|
|
|
Civil Rights Museum--Phase 3 (Addition)
|
Complete
|
$1,300,000
|
$-
|
|
Cultural
|
2003-2008
|
Design, construct and equip 800 SF addition to the existing museum. The addition will include a banquet facility that will accommodate 400 people for community meetings, private/public affairs and museum projects. (460 MLK, Jr. Blvd.)
|
|
|
General Drainage
|
Complete
|
$500,000
|
$-
|
|
Drainage
|
2003-2008
|
Funds for miscellaneous capital equipment purchases.
|
|
|
Little Hurst Canal
|
Complete
|
$108,000
|
$-
|
|
Drainage
|
1998-2003
|
Increase size of culvert crossing at railroad, east of SR 21.
|
Project design was completed, permitted and bid. However, single bid exceeded budget by 3X and was not awarded. Project on hold.
|
Project includes capacity upgrade to existing drainage culverts beneath CSX railroad tracks. Features include replacing existing 48" culvert pipes with e 72" culvert pipes.
|
Louis Mills/Redgate/Rahn Dairy Canal Phase 1
|
Complete
|
$2,350,000
|
$-
|
|
Drainage
|
1998-2003
|
Improve channel and increase size of culvert crossings from railroad through Garrard Avenue (Louis Mills and Red Gate Canals).
|
Work from Garrard completed in 2010. Rahn Dairy was designed and property purchased, but was not constructed. Marshall Branch Phase 1 was completed in 2016.
|
The Louis Mills section extends from CSX railroad track at boundary to HAAF to Lynes Parkway. The Rahn Dairy Canal section extends from north to south of Buckhalter Rd. Features include widening canals and increasing culvert crossings at roadways.
|
Louis Mills/Redgate/Rahn Dairy Canal Phase 2
|
Complete
|
$-
|
$-
|
2010
|
Drainage
|
1998-2003
|
Improve channels and increase size of culvert crossings from Garrard Avenue to I-516.
|
|
|
Lucas Theater: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$833,000
|
$-
|
09/16/2003
|
Cultural
|
1998-2003
|
Providing funding through contract for renovation of historic theater (32 Abercorn St).
|
|
Public funds matched private contributions to complete the project. With the 1993-1998 SPLOST, the 1998-2003 SPLOST and federal and city funding, public funds contributed about 25% of the project`s capital cost.
|
Melinda Dr. (Stiles Ave. Extension)
|
Complete
|
$-
|
$-
|
|
Roads
|
1998-2003
|
City of Savannah has not identified a need or purpose for the project.
|
|
|
Ogeechee Canal: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$833,000
|
|
|
Cultural
|
1998-2003
|
Provide trail, including interpretive markers and bridges, along the historic Savannah-Ogeechee Canal.
|
Project scheduled for award of engineering services in mid-2005 for permit and trail design. Construction should begin on trail by early 2006.
|
Budgeted amount $833,000. Board of Commissioners authorized agreement with Savannah-Ogeechee Canal Society to manage the project in conformance with master plan. The Canal Society, however, opted not to assume responsibility.
|
Ogeechee Farms Drainage - Phase 2
|
Complete
|
$700,000
|
$-
|
2011
|
Drainage
|
1998-2003
|
Improve channels, increase size of culverts at crossings and provide access for maintenance.
|
|
Project extends from Vidalia Road downstream to Phase 1.
|
Other Capital Outlay (1998) - Vernonburg
|
Complete
|
$87,053
|
$-
|
09/16/2003
|
Other
|
1998-2003
|
"Other Capital Outlay" provided muncipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
Complete means County issued check. Town of Vernonburg assumed responsibility by contract to expend funds in accordance with state law.
|
By resolution and intergovernmental in accordance with state law, Chatham County provided funds for municipal eligible projects. Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
Other Capital Outlay--Chatham County to Senior Citizens
|
Complete
|
$50,000
|
|
09/01/1999
|
Other
|
1998-2003
|
Capital outlay for kitchen renovation on behalf of Senior Citizens (3025 Bull Street).
|
"Complete" means Chatham County issued check to Senior Citizens in accordance with agreement.
|
In conformance with the SPLOST resolution, by contract Chatham County distributed funds to Senior Citizens for a capital outlay project that serves a community need. Senior Citizens matched the county funds with private donations to complete the project
|
Pipemakers Canal Widening Project, Golf Course
|
Complete
|
$244,000
|
$-
|
02/20/2001
|
Drainage
|
1998-2003
|
Improve 5000 feet +/- of channel and provide access for maintenance.
|
|
Project extends from west end of Savannah/Hilton Head Intn`l. Airport to I-95. Features include widening of the canal and increasing the size of culvert crossings at roadways.
|
Pipemakers Canal Widening Project, Phase 1
|
Complete
|
$12,500,000
|
$-
|
2008
|
Drainage
|
1998-2003
|
Constructed new flood control structure with sluice gates and removed old tide gates. Improved approximately 10,000 feet of channel and provided access for maintenance.
|
|
Project extends from outfall of canal at the Savannah River to upstream of SR25. Features include widening of the canal, erosion protection and replacing the tidegate structure with a new sluice gate structure having greater capacity.
|
Pipemakers Canal Widening Project, Phase 2, Section 1
|
Complete
|
$8,000,000
|
$-
|
2012
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements and provide access for maintenance upstream of SR 21 through SR 307.
|
|
Project extends from west of SR22 to Dean Forest Road. Features include widening of the canal and other improvements to facilitate better flow of storm water.
|
Pipemakers Canal Widening Project, Phase 3
|
Complete
|
$200,000
|
$-
|
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements and provide access for maintenance upstream of I-95 through US 80.
|
Project shelved as the work is in Pooler. May be reopened if agreement is reached. Most funding repuposed.
|
Project extends from I-95 to near US80 in Bloomingdale. Features include widening of the canal and increasing the size of culvert crossings at roadways.
|
Pipemakers Canal Widening Project, Pump Station
|
Complete
|
$600,000
|
$-
|
2014
|
Drainage
|
1998-2003
|
Study to determine feasibility and benefits of constructing pump station.
|
|
Study determined that construction of pump station did not provide significant benefit and reduction in water levels. Recommendation was not to construct pump station.
|
Placentia Canal - Phase 2
|
Complete
|
$2,400,000
|
$-
|
12/02/2003
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements and provide maintenance access from Bonaventure through Shell Road.
|
|
Project limits extend from Bonaventure Road to Shell Road. Features include widening of the canal and increasing the size of culvert crossings at roadways. Ph 1 was the construction of a tidegate structure south of Bonaventure Road completed in 2/2/1999
|
Pooler--"Other Capital Outlay" (1998)
|
Complete
|
$458,703
|
$-
|
09/16/2003
|
Other
|
1998-2003
|
"Other Capital Outlay" provided muncipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
"Complete" means the County issued check. City of Pooler assumed responsibility by contract to expend funds in accordance with state law.
|
By resolution and intergovernmental in accordance with state law, Chatham County provided funds for municipal eligible projects. Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
Port Wentworth--"Other Capital Outlay" (1998)
|
Complete
|
$458,703
|
$-
|
09/16/2003
|
Other
|
1998-2003
|
"Other Capital Outlay" provided muncipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
"Complete" means County issued check. City of Port Wentworth assumed responsibility by contract to expend funds in accordance with state law.
|
By resolution and intergovernmental in accordance with state law, Chatham County provided funds for municipal eligible projects. Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
Quacco Canal/Aquatic Restoration
|
Complete
|
$1,648,000
|
$-
|
2007
|
Drainage
|
1998-2003
|
Design and construct improvements to restore natural flow regime and reestablish marsh vegetation to create Salt Water Mitigation Bank.
|
|
Project includes removal of rice box at outfall and increasing the size of driveway culverts to increase flow capacity.
|
Quacco Canal/Regency Park
|
Complete
|
$1,582,000
|
$-
|
2009
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements from Quacco Canal to Quacco Trail. Features include new storm collector pipe along Quacco Road.
|
|
|
Rice Mill at Grove Point Road
|
Complete
|
$420,000
|
$-
|
2001
|
Drainage
|
1998-2003
|
Design and construct storm water drainage improvements and provide access for maintenance from Wild Heron Road to Grove Point Road.
|
|
Features include widening of the canal and increasing the size of culvert crossings at the maintenance road.
|
Savannah--"Other Capital Outlay" (1998)
|
Complete
|
$16,292,341
|
$-
|
09/16/2003
|
Other
|
1998-2003
|
"Other Capital Outlay" provided muncipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
Project complete means County issued check. City of Savannah assumed responsibility by contract to expend funds in accordance with state law.
|
By resolution and intergovernmental in accordance with state law, Chatham County provided funds for municipal eligible projects. Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
Senior Citizens--Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$50,000
|
$-
|
|
Other
|
1998-2003
|
Capital outlay for kitchen renovation on behalf of Senior Citizens (3025 Bull Street).
|
"Complete" means Chatham County issued check to Senior Citizens in accordance with agreement.
|
In conformance with the SPLOST resolution, by contract Chatham County distributed funds to Senior Citizens for a capital outlay project that serves a community need. Senior Citizens matched the county funds with private donations to complete the project.
|
Spur 21/Benton Dr., Phase I
|
Complete
|
$1,175,863
|
|
|
Roads
|
1998-2003
|
Construct a two lane road on four lanes of right-of-way on new location from north of Pooler Parkway to the Jimmy DeLoach Parkway.
|
|
Chatham County has budgeted $1,500,000 for this project, part of which was reimbursed through a County Contract with GDOT.
|
Garden City: Other Capital Outlay (1998)
|
Complete
|
$458,703
|
$-
|
09/01/2003
|
Other
|
1998-2003
|
"Other Capital Outlay" provided muncipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
Project "complete" means County issued check. City of Garden City assumes responsibility by contract to expend funds in accordance with state law.
|
Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
Georgetown Canal at St. Ives
|
Complete
|
$208,360
|
$-
|
01/01/2007
|
Drainage
|
1998-2003
|
Increase the size of culvert crossing St. Ives Way.
|
|
|
Golden Isles Drainage - Phase 2
|
Complete
|
$560,000,000
|
$-
|
10/11/2007
|
Drainage
|
1998-2003
|
Construct larger storm pipes and improve drainage swales from Tropical Way to Quarterman Dr along Golden Isles Way and south along Quarterman Dr to Tropical Way.
|
|
|
Greenbriar: Chatham County -"Other Capital Outlay" (1998).
|
Complete
|
$1,258,000
|
$-
|
09/01/2003
|
Other
|
1998-2003
|
Provide funds for expansion and renovation of childrens care center (Hopkins Avenue, City of Savannah).
|
"Complete" means County issued payments for the project in accordance with a written agreement. Greenbriar assumed responsibility by contract to expend funds in accordance with state law.
|
By resolution and in accordance with state law, Chatham County provided funds by contract to Greenbriar for renovation and expansion of facilities for youth services, which serve a public benefit.
|
Greenway Fund (1998)
|
Complete
|
$-
|
|
09/16/2003
|
Other
|
1998-2003
|
SPLOST 1993-1998 provided $9 million to be distributed among municipalities and Chatham County (unincorporated area) for greenways/ bikeways/open space in concert with Chatham County Open Space Plan.
|
A supplemental agreement between Chatham County and municipalities provided a distribution formula for the funding. "Complete" means funds were distributed in accordance with agreement.
|
As per the SPLOST resolution and agreement, this fund represents a budget of $9 million, which was distributed to cities and unincorporated area of greenways/bikeways/open space. The amount of funding appears within the name of each municipality.
|
Greenway Fund--Civil War Heritage Trail
|
Complete
|
$5,000
|
|
|
Cultural
|
1998-2003
|
Funds to participate in state Civil War Heritage Trail project. Funded historic markers in Chatham County that designated historically-significant areas of Sherman's March to the Sea as part of statewide project.
|
|
|
Greenway Fund--Demere Property Acquisition
|
Complete
|
$5,575,333
|
$-
|
10/04/2000
|
Other
|
1998-2003
|
Acquired 150 acres on Whitemarsh Isl (corner of Johnny Mercer & Bryanwood) from the Chatham County share of 1998 Greenway Fund. Of the 150 ac in the acquisition from the Demere family, 120 ac remains placed in conservation easements.
|
|
State of Georgia reimbursed $2,151,500 under State Greenspace Program. Property includes 30 acres of marsh, 90 acres wetlands and 30 acres uplands. Besides conservation easement, covenants protect 30 acres of uplands.
|
Greenway Fund--DNR Georgia Greenway
|
Complete
|
|
|
|
Other
|
1998-2003
|
Matching requirement for Greenway funds
|
|
|
Greenway Fund--Garden City
|
Complete
|
$87,976
|
|
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
Project complete means Chatham County issued check. Garden City assumed responsibility by contract to expend funds in accordance with state law.
|
Chatham County issued check to the City of Garden City for use in greenway/bikeway/open space projects.
|
Greenway Fund--Pooler
|
Complete
|
$62,228
|
|
09/16/2003
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
Project complete means Chatham County issued check. Pooler assumed responsibility by contract to expend funds in accordance with state law.
|
Chatham County issued check to City of Pooler for use in greenway/bikeway/open space projects.
|
Greenway Fund--Port Wentworth
|
Complete
|
$42,808
|
|
09/16/2003
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
Project complete means Chatham County issued check. Port Wentworth assumed responsibility by contract to expend funds in accordance with state law.
|
Chatham County issued check to City of Port Wentworth for use in greenway/bikeway/open space projects.
|
Greenway Fund--Savannah
|
Complete
|
$2,841,996
|
|
09/16/2003
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
Project complete means Chatham County issued check. City of Savannah assumed responsibility by contract to expend funds in accordance with state law.
|
Chatham County issued check to City of Savannah for use in greenway/bikeway/open space projects.
|
Greenway Funds--Bloomingdale
|
Complete
|
$98,373
|
|
09/16/2003
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
Project complete means Chatham County issued check. Bloomingdale assumed responsibility by contract to expend funds in accordance with law.
|
Chatham County issued check to Bloomingdale for use in greenway/bikeway/open space projects.
|
Greenway Fund--Thunderbolt
|
Complete
|
$30,246
|
|
09/16/2003
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
"Complete" means Chatham County issued payments per the agreement. Thunderbolt assumed responsibility by contract to expend funds in accordance with state law.
|
Chatham County issued check to Town of Thunderbolt for use in greenway/bikeway/open space projects.
|
Greenway Fund--Tybee Island
|
Complete
|
$33,646
|
|
09/16/2003
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
Project complete means Chatham County issued check. Tybee Island assumed responsibility by contract to expend funds in accordance with law.
|
Chatham County issued check to the City of Tybee Island for use in greenway/bikeway/open space projects.
|
Greenway Fund--Vernonburg
|
Complete
|
$2,531
|
|
09/16/2003
|
Other
|
1998-2003
|
Part of $9 million in SPLOST 1993-1998 designated for greenways/bikeways/ open space in concert with Chatham County Open Space Plan.
|
Project complete means Chatham County issued check. Vernonburg assumed responsibility by contract to expend funds in accordance with state law.
|
Chatham County issued check to Town of Vernonburg for use in greenway/bikeway/open space projects.
|
Halcyon Bluff Drainage
|
Complete
|
$1,127,000
|
$-
|
01/01/2008
|
Drainage
|
1998-2003
|
Construct larger storm pipes and improve drainage ditches from Garland Drive to Halcyon Drive, and from Halcyon Drive to Lavon Avenue.
|
|
Additional outfall drainage improvements added to the original project at the intersection of Halcyon Drive and Lavon Avenue.
|
Hardin Canal - Phase 1
|
Complete
|
$9,372,000
|
$-
|
12/2013
|
Drainage
|
1998-2003
|
Construct two larger drainage culverts at SR 307 and provide access roads for maintenance.
|
|
|
Henderson Canals
|
Complete
|
$1,556,000
|
$-
|
2010
|
Drainage
|
1998-2003
|
Increase the size of Little Neck Canal culvert crossings at Little Neck Road, Henderson Oaks, and for a golf cart path.
|
|
Project limits extend from Little Neck Rd to Al Henderson Blvd, and from Little Neck Rd to Brown Thrush Rd.
|
Hodgson Memorial Dr.
|
Complete
|
$157,646
|
|
|
Roads
|
1998-2003
|
Widening between Mall Boulevard and Eisenhower Drive
|
|
Accomplished by the City of Savannah under agreement with the GDOT for partial reimbursement. The County reimbursed the City for the local cost in accordance with the SPLOST resolution.
|
Hutchinson Island Riverwalk Extension--Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$1,700,000
|
|
|
Other
|
1998-2003
|
Extends riverwalk 2,150 linear ft around the perimeter of Slip 1 on Hutchinson Isl. Project provides addt. pedestrian access, historic interpretative trail and sheetpile/dredging of slip for possible development into yachting basin (privately developed).
|
Project pending until release of federal and state permits because of dredging, mitigation of wetlands and exploration of cultural resources (Fig Island Derelict).
|
Approved and funded local project agreement with Georgia Department of Transportation will fund 80% of construction cost, (estimated at $8 million).
|
Kingsway Canal
|
Complete
|
$1,240,000
|
$-
|
04/01/2011
|
Drainage
|
1998-2003
|
Improve channel and increase size of culverts at crossings upstream of the Truman Parkway.
|
|
Project extends from west of Whitfield Avenue to Kings Way. Features include widening of the canal and increasing the size of culvert crossings at roadways.
|
King-Tisdell: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$1,258,000
|
$-
|
09/16/2003
|
Cultural
|
1998-2003
|
By contract, provide funding to King-Tisdell Foundation for renovations to the historic King-Tisdell Cottage and Beach Institute. (514 East Huntingdon St)
|
|
In accordance with SPLOST resolution and agreement, Chatham County funded this project on behalf of the King-Tisdell Foundation. The Foundation conveyed ownership of the properties to Chatham County as a safeguard to expenditure of public funds.
|
Library (Technology)--Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$725,656
|
|
|
Cultural
|
1998-2003
|
Computer equipment, software and other technology components for modernization on behalf of library patrons. (Live Oak Library)
|
|
|
Whitefield Ave. Widening (Hendry to Ferguson)
|
Complete
|
$1,684,747
|
$-
|
|
Roads
|
1993-1998
|
Widening from two lanes to four lanes including intersection improvements.
|
Estimated completion November 2013.
|
County paid for design and right-of-way acquisition. GDOT is funding remaining construction costs with federal and state funds.
|
Whitemarsh Island Community Center
|
Complete
|
$353,086
|
|
01/24/1999
|
Cultural
|
1993-1998
|
Design, construct and equip a 4,000- square foot community center to be used for community meetings, county programs, and private affairs. (170 Whitemarsh Island Rd)
|
Chatham County Department of Public Works and Parks Services manages the center.
|
The 1993-1998 SPLOST included a provision that interest earnings could be used to fund projects (eligible under State law) from the County's 5-Year Capital Improvement Program. This project became funded through interest earnings.
|
Wilmington Island Community Park (Cohen St., Wilmington Island)
|
Complete
|
$81,465
|
$-
|
|
Recreation
|
1993-1998
|
Renovation of community park on Wilmington Island. Project included construction of restrooms, renovation of picnic pavilion and playground equipment.
|
|
The 1993-1998 SPLOST included a provision that interest earnings could be used to fund projects (eligible under state law) from Chatham County`s 5-Year Capital Improvement Program. This recreational project became funded through interest earnings from SPLOST.
|
Woodville Community Center
|
Complete
|
$227,482
|
$-
|
12/31/1995
|
Cultural
|
1993-1998
|
Design, construct and equip 4,000 square foot community center to be used for community meetings, city programs, and private affairs. (132 Darling St)
|
The City of Savannah operates the center.
|
The center was designed and built cooperatively with Hudson Hill Community Center.
|
Abercorn Widening from Rio Rd. to Truman Pkwy.
|
Complete
|
$112,765
|
$-
|
|
Roads
|
1998-2003
|
To widen Abercorn St. from six lanes to eight lanes from Rio Rd. to the intersection of the Truman Parkway, Phase V.
|
Concept report is pending approval by the GDOT.
|
|
Atlantic Creosote Drainage
|
Complete
|
$760,000
|
$-
|
12/31/2002
|
Drainage
|
1998-2003
|
Design and construct widening of the Phillips Canal, replace culvert and tidegate.
|
Project completed and turned over to Port Wentworth
|
Project limits extend from the Savannah River to Barnsley Street.
|
Bloomingdale--"Other Capital Outlay" (1998)
|
Complete
|
$458,703
|
$-
|
|
Other
|
1998-2003
|
"Other Capital Outlay" provided municipalities with funds to complete eligible (as defined by state law) projects within their incorporated boundaries.
|
"Complete" means Chatham County issued check; City of Bloomingdale assumes responsibility by contract to expend funds in accordance with state law.
|
By resolution and intergovernmental in accordance with state law, Chatham County provided funds for municipal eligible projects. Examples of eligible projects include roads and streets, parks, public buildings, sidewalks, water and sewer projects.
|
CEMA Equipment: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$227,143
|
|
06/30/2003
|
Other
|
1998-2003
|
Replace and upgrade emergency warning system for the Chatham Emergency Management Agency.
|
|
|
Chatham County: Other Capital Outlay (1998)
|
Complete
|
$-
|
$-
|
|
Other
|
1998-2003
|
Chatham County's share of "Other Capital Outlay" category as shared with municipalities for local projects as eligible under state law. The County distributed its share of funds to community organizations and for certain county facilities.
|
Complete means Chatham County distributed the funds in accordance with contracts executed with certain community organizations.
|
In accordance with SPLOST resolution and agreement as required by state law, the 1998-2003 SPLOST included a category of funding. Each listing of funds distributed by Chatham County includes specific details of the project. Total equaled $14,112,663.
|
Conaway Branch Canal
|
Complete
|
$1,265,000
|
$-
|
09/01/2010
|
Drainage
|
1998-2003
|
Widen canal and increase size of culvert crossings under roadways from Main St (Bloomingdale) to Pipemakers Canal.
|
|
|
Bay St. Widening
|
On Going
|
$14,000,000
|
$-
|
|
Roads
|
1998-2003
|
Bay St. from I-516 to Bay St. Viaduct.
|
Project is currently under construction by Reeves Construction and is approximately 75% complete.
|
|
East/West Corridor
|
On Going
|
$12,000,000
|
$-
|
|
Roads
|
1998-2003
|
Being studied to determine the best way of improving traffic flow from east to west across the City of Savannah.
|
Project is on-going. Funds from this project were used towards DeRenne Avenue Improvements, I-16 at SR 307 and traffic studies along I-16.
|
$18,000,000 is budgeted for this project. Project by the City of Savannah
|
Eisenhower Widening and Median
|
On Going
|
$3,500,000
|
$-
|
|
Roads
|
1998-2003
|
Addition of a raised median and left turn lanes to provide better traffic control between Hodgson Memorial Drive and Waters Ave.
|
Project is solely in the City of Savannah. City could not commit to improvements, so design work halted. City of Savannah needs to complete design, acquire right of way, adjust utilities and construct the project.
|
Budgeted at $3,500,000.
|
Greenway Fund--Coastal Georgia Greenway
|
Construction
|
$505,431
|
$-
|
09/16/2003
|
Recreation
|
1998-2003
|
SPLOST Greenway Fund provided match for state grant for $400,000 for the Coastal Ga. Greenway project, a 141-mile trail through six coastal Georgia counties. The County serves as lead applicant in developing master plan & design.
|
Master plan: complete. Routing plan: complete. Chatham County "Pilot Projects" -- Truman Linear Park and S&O Canal Trail
Construction of the Truman Linear Park Trail, Phase 2A is underway.
|
Completion of the plan would total some $90 million through all six counties; however, each county/city remains responsible for funding sections within its limits. Included in Chatham are Truman Linear Park and S&O Canal Trail.
|
I-16 at Little Neck Road/Jimmy DeLoach Parkway Interchange
|
Concept
|
$2,000,000
|
|
On Going
|
Roads
|
1998-2003
|
Project will look at operational and safety improvements required at the interchange.
|
Staff obtained a grant through the MPO to complete an interchange study for the project. The results of the study will be used to partner with GDOT to develop short term and long term operational and safety improvements for the interchange. Staff will work with GDOT to obtain construction funding for future projects.
|
|
Interstate 16 at State Route 307
|
Design
|
$2,000,000
|
$34,000,000
|
On Going
|
Roads
|
1998-2003
|
Project will construct a new bridge and interchange for Interstate 16 at State Route 307. New interchange will be a Diverging Diamond Interchange.
|
County completed 30% set of construction plans to facilitate GDOT awarding a design-build contract for the project. Project bids came in over budget and GDOT is determining if it can find additional funds to award the project.
|
|
Port Industrial Canal
|
Complete
|
$750,000
|
$-
|
|
Drainage
|
1998-2003
|
Project is On Hold Indefinitely. Design and construct storm water drainage improvements and provide maintenance access between Pipemakers Canal and SR 307.
|
|
Project extends from Pipemakers Canal to SR307. Features include widening of the canal and increasing the size of culvert crossings at roadways.
|
EMS: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$79,982
|
$-
|
|
Other
|
1998-2003
|
Provided funds for new EMS unit.
|
|
Identified as "Other Capital Outlay", provided funds for specific city & County projects. The County directed its funds for community projects by non-profit organizations, selected County equipment and supplemental project needs.
|
Fawcett Canal - Lagoon Modifications
|
Complete
|
$340,584
|
$-
|
12/31/2004
|
Drainage
|
1998-2003
|
Regrade banks of lagoons and add erosion control features on lagoons north and south of Dovetail Crossing (Georgetown).
|
|
|
Fawcett Canal - Phase 2
|
Complete
|
$1,114,000
|
$-
|
06/15/2005
|
Drainage
|
1998-2003
|
Construct larger storm pipes from lagoons at Dovetail Crossing to White Hawthorne Dr.
|
|
|
Romney Place/Parkersburg - Phase 2, Parkersburg Road
|
Complete
|
$747,000
|
$-
|
|
Drainage
|
1998-2003
|
Project is On Hold Indefinitely. Design and construct storm water collector system piping improvements from Romney Place along Parkersburg Road to outfall at Moon River.
|
|
Features include new larger storm pipe having greater flow capacity along Parkersburg Road.
|
Fire Departments: Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$2,040,000
|
$-
|
|
Other
|
1998-2003
|
Provided funds for equipment purchases for municipal and volunteer fire departments.
|
"Complete" means Chatham County has provided funding in accordance with agreements.
|
Per SPLOST resolution and agreement, the County made payments totaling $226,660 over 5 years to all fire departments, including Bloomingdale, Garden City, Pooler, Port Wentworth, Savannah, Thunderbolt, Tybee Island, Southside and Isle of Hope.
|
Pooler Pkwy. from Quacco Rd. to Pine Barren Rd.
|
Complete
|
$539,897
|
$4,070,000
|
06/16/2000
|
Roads
|
1993-1998
|
Construction of a new four lane divided road, including a new interchange at I-16.
|
|
Chatham County paid for the design and purchased the right-of-way for this project. GDOT paid for the construction.
|
President Street
|
Complete
|
$1,232,316
|
|
06/12/2002
|
Roads
|
1993-1998
|
Addition of curbing to the median and regrading of the roadway with asphalt paving to provide better drainage to eliminate standing water on the roadway.
|
|
|
Romney Place/Parkersburg Drainage - Phase 1, Central Ave.
|
Complete
|
$280,000
|
$-
|
11/09/2001
|
Drainage
|
1993-1998
|
Design and construct storm water collector system piping improvements from Paxton Drive along rear of 5 properties, crossing Central Avenue.
|
|
|
Runaway Point Park - Phase 1
|
Complete
|
$880,615
|
|
|
Recreation
|
1993-1998
|
Funds provided for acquisition of property, development of master plan and completion of Phase 1, including ballfields, picnic pavilion, youth playground, perimeter trail and landscaping. (Causton Bluff Road)
|
Phase 1 funded through 1993-1998 SPLOST. Phase 2, including pavilion, restrooms and tennis court, will be funded through 2003-2008 SPLOST.
|
|
S.R. 26/U.S. 80 from Bryan Wood Rd. to the Bull River
|
Complete
|
$130,124
|
$10,000,000
|
|
Roads
|
1993-1998
|
The widening of the road from two lanes to four lanes including a new bridge over Turner's Creek.
|
|
|
S.R. 26/U.S. 80 from the Bull River to Lazaretto Creek
|
Complete
|
$-
|
$-
|
|
Roads
|
1993-1998
|
The widening of S.R. 26/U.S. 80 from two lanes to four lanes including a new bridge over the Bull River.
|
|
The County will participate in any reimbursable utility relocations. The County has budgeted $100,000 for this purpose. GDOT will pay for design & construction with federal & state funds. The estimated cost is $70,000,000.
|
Savannah State Olympic Track and Field
|
Complete
|
$997,082
|
$-
|
05/13/1995
|
Recreation
|
1993-1998
|
Construction of track and field facilities at Savannah State's T. A. Wright Stadium.
|
|
County reimbursed SSU, who managed the contract. The project was approved in 1993 SPLOST referendum.
|
Science Dr. Relocation
|
Complete
|
$1,261,695
|
$-
|
06/30/2000
|
Roads
|
1993-1998
|
The realignment of a two lane road, Science Drive, off of the Armstrong campus on new location.
|
|
|
Shackelford Pkwy. Lighting--from Chatham County "Other Capital Outlay" (1998)
|
Complete
|
$200,000
|
|
02/01/2004
|
Other
|
1993-1998
|
Participate with Trade Center Authority in funding Shackelford Parkway streetscape program, including landscaping, irrigation and signage.
|
|
This project, as an extension of the Hutchinson Island Interchange/Entry Road Project (approved 1993-1998 SPLOST), became funded through interest earnings from SPLOST fund.
|
Soccer Complex
|
Complete
|
$2,832,317
|
|
03/18/1996
|
Recreation
|
1993-1998
|
Project to design, construct and equip soccer complex, (Sallie Mood Dr.) including eight fields for competitive play. Lighting provided for all eight fields.
|
|
1993-1998 SPLOST: $1,500,000 1995 Referendum: $700,000 Additional funding for this recreational project became available through interest earnings from SPLOST fund.
|
Stagecoach Road
|
Complete
|
$228,993
|
$92,404
|
|
Roads
|
1993-1998
|
The paving and drainage of 0.3 mile of Stagecoach Road beginning at S.R. 26/U.S. 80.
|
|
|
Tatemville Community Center--Phase 1
|
Complete
|
$517,260
|
$-
|
06/08/2000
|
Cultural
|
1993-1998
|
Design, construct and equip a 4,000 square foot community center to be used for community meetings, city programs and private affairs(333 Coleman St).
|
City of Savannah maintains the Tatemville Community Center.
|
The center was built on the site of an existing city-owned community park. Architect/Contractor (Design-Build): L. Scott Barnard & Associates, AIA. Contractor: DMK Construction, Inc.
|
Telfair
|
Complete
|
$1,000,000
|
|
09/16/1998
|
Cultural
|
1993-1998
|
Capital outlay for renovation of historic Owens-Thomas House on behalf of Telfair.
|
At the completion of the project plus five years, Chatham County returned the property to Telfair.
|
As per the SPLOST resolution, the County distributed funds to Telfair for a capital outlay project that serves a community purpose. Telfair matched the funds with private donations to complete the project. The County received title to the property.
|
Thunderbolt Complex
|
Complete
|
$225,000
|
|
09/16/1998
|
Other
|
1993-1998
|
Funds provided to the Town of Thunderbolt for its municipal complex project.
|
"Completed" means funds provided to Thunderbolt per the resolution and agreement adopted prior to the referendum.
|
In the 1993-1998 SPLOST, the County allocated funds for street paving based on a formula to all cities. Thunderbolt requested that its funds for streets be directed to its municipal complex project (new town hall and police station).
|
Track & Field - Wright Stadium
|
Complete
|
$1,062,980
|
|
05/13/1995
|
Recreation
|
1993-1998
|
Design and construct Olympic-quality 400-meter track and competitive field events at Wright Stadium as part of "Olympic Legacy" package.
|
The completed project remains open to the public.
|
Through agreement with the University Board of Regents, Savannah State University accepted track and field improvements. Designer: Athletic Facilities Consulting Contractor: Athletic Facilities Consulting and Southeast Recreational Industries, Inc.
|
Trade Center (Hutchinson Island)
|
Complete
|
$8,356,628
|
$-
|
05/22/2000
|
Other
|
1993-1998
|
Design, construct and equip 345,000 square foot facility that would allow the community to compete for 85-90% of all conventions, expositions and trade shows.
|
Property leased to Trade Center Authority for management and operations.
|
Project funded through SPLOST 1993-1998 of $37 million and voter-approved $15 million in 1995; state funding of $182 million; with related road work funded through SPLOST(Roads). Architect: TVSTA (Atlanta). Builder: Maritime Trade Center Builders
|
Trade Center: DCA Grant (Hutchinson Island)
|
Complete
|
$3,300,000
|
$-
|
12/12/2002
|
Other
|
1993-1998
|
Georgia Department of Community Affairs provided grant to acquire Parcel 7 on Hutchinson Island. Parcel 7 (immediately west of the Trade Center) to develop for purposes related to furthering the mission of the Trade Center.
|
In 2003, Chatham County leased Parcel 7 to the Trade Center Authority as part of its master lease for operations and maintenance of the convention center.
|
The State DCA grant funded the purchase of Parcel 7 (13 ac of upland and 7 ac of water within Slip 3) on the adjoining tract. For accounting purposes, the funding was included in the SPLOST revenue and expenditure report.
|
Tremont Park
|
Complete
|
$40,000
|
|
|
Recreation
|
1993-1998
|
Funds for community park for Tremont area of Savannah.
|
"Complete" means funds provided in accordance with agreement.
|
The 1993-1998 SPLOST included a provision that interest earnings could be used to fund projects (eligible under state law) from the County's 5-Year Capital Improvement Program. This recreational project became funded through SPLOST interest earnings.
|
Triplett Park--Phase 1
|
Complete
|
$2,639,840
|
$-
|
12/12/2000
|
Recreation
|
1993-1998
|
Provide funds for master plan and phase 1 to design, construct and equip major regional park to serve West Chatham County. Project included construction of lake, perimeter asphalt trail, paved entry road and utility extensions.
|
|
SPLOST 1993-1998 funded Ph. I. SPLOST 1998-2003 includes $500,000 for S&O Canal Trail and trailhead (restrooms) facilities to match state grant. SPLOST 2003-2008 includes $1.7 million for Ph. 2.
|
Truman Linear Park, Phase 1
|
Complete
|
$263,797
|
|
|
Recreation
|
1993-1998
|
Provides funding for master plan for 6.5-mile asphalt trail that will connect Daffin Park to Lake Mayer Regional Park along path of Truman Parkway and construction of Phase 1 (Police Memorial Trail).
|
Phase 2 remains pending funding of section from current terminus at Police Memorial Drive to Lake Mayer. Estimated cost at $1.6 million.
|
Though the $300,000 budget intended only to fund the master plan and engineering, use of a grant funded portions of the planning costs to allow construction of Phase 1, known as Police Memorial Trail.
|
Truman Pkwy., Phase 5 (Sales Tax 2)
|
Complete
|
$1,083,725
|
|
|
Roads
|
1993-1998
|
Extension of the Harry S. Truman Parkway (four lane divided limited access road) from Whitefield Ave. to Abercorn St.. Includes bridge over the Vernon River and at-grade intersections at Abercorn St.
|
|
This is for additional funds needed not included in "Fund 320" (the initial fund source for the project).
|
Tybee Pier & Pavilion (14th St., Tybee Island)
|
Complete
|
$2,644,746
|
$-
|
|
Recreation
|
1993-1998
|
Design, construct and equip pier and pavilion.
|
Known as Tybrisa II, a modern-day version of the historic Tybrisa Pier and Pavilion which previously was situated at the site.
|
The 1993-1998 SPLOST included a provision that interest earnings could be used to fund projects (eligible under state law) from Chatham County`s 5-Year Capital Improvement Program. Architect: Lockwood-Greene (Savannah). Contractor: TIC
|
Youth Football
|
On Going
|
$1,700,000
|
|
|
Recreation
|
1993-1998
|
Construct youth football fields
|
Site is unknown.
|
|
Humane Society Road
|
Complete
|
$152,107
|
$22,541
|
02/19/2003
|
Roads
|
1993-1998
|
Paved the dirt road and parking lot at the Humane Society (from the entrance at Sallie Mood to County storage facilities).
|
|
|
Hutchinson Island Interchange & Shackelford Blvd.
|
Complete
|
|
$11,049,000
|
|
Roads
|
1993-1998
|
Construction of a new Interchange on S.R. 404 Spur/U.S. 17 at the Talmadge Bridge, and construction of a four lane road with a raised median to the Trade Center (included a bridge and road connector to Grand Prize of America loop road).
|
|
The County's cost for this project was for R/W acquisition and for the bridge connecting Resort Dr. to the Westin Hotel. The $15,950,742 shown in the financial report is the total set aside, most of which went to the Trade Center.
|
Hutchinson Island Loop Road
|
Complete
|
$2,865,775
|
$-
|
07/01/1996
|
Roads
|
1993-1998
|
The construction of a new loop road (Grand Prize of America Dr.) on new location that ties into Resort Dr. and Shackelford Blvd. on Hutchinson Is.
|
|
|
Hutchinson Island Water & Sewer
|
Complete
|
$6,101,633
|
$-
|
|
Other
|
1993-1998
|
Extend utilities (water, sewer, irrigation) to Hutchinson Island via three directional bores beneath Savannah River with double-loop interconnection to city service.
|
Final project pending completion of President Street water pump station.
|
Three directional bores (water, sewer and treated effluent for golf course) and Hutchinson Island double-loop interconnect to City of Savannah complete.
|
Inclusive Confidence Course
|
Complete
|
$39,500
|
|
01/30/1997
|
Recreation
|
1993-1998
|
Funds part of development and installation of recreational course with various stations to promote good health. (May Howard Elementary School)
|
Maintained by School Board. Though situated on school property, course remains open to the public during non-school hours.
|
The 1993-1998 SPLOST included a provision that interest earnings could be used to fund projects (eligible under state law) from the County's 5-Year Capital Improvement Program. This project became funded through interest earnings from SPLOST fund.
|
Jaycee Park Tennis Courts
|
Complete
|
$13,581
|
|
|
Recreation
|
1993-1998
|
Resurface tennis courts. They are the only public tennis courts on Wilmington Island.
|
Pending resolution of property dispute.
|
The 1993-1998 SPLOST included a provision that interest earnings could be used to fund projects (eligible under state law) from the County's 5-Year Capital Improvement Program. This project became funded through interest earnings from SPLOST Fund.
|
Jimmy DeLoach Pkwy. Interchange at S.R. 21
|
Complete
|
$9,363,503
|
$1,300,000
|
|
Roads
|
1993-1998
|
A new interchange for the Jimmy DeLoach Parkway at S.R. 21. Includes a bridge over S.R. 21 and a new road connecting Flonnel Ave. to S.R. 21.
|
|
|
Juvenile Justice Center
|
Complete
|
$4,650,838
|
|
10/31/1997
|
Other
|
1993-1998
|
Design, construct and equip a 20,800 square foot building for juvenile court offices, courtrooms and services (197 Carl Griffin Drive).
|
|
Per SPLOST resolution and intergovernmental agreement, this project relocated Juvenile Court from Eisenhower Dr. as part of expanded complex for juvenile services, including the State's relocation of the Regional Youth Detention Center.
|
King George Blvd. Intersection Improvements
|
Complete
|
$830,142
|
$-
|
06/30/2000
|
Roads
|
1993-1998
|
Addition of left turn lanes and new signals to improve level of service at the intersection.
|
|
Done by County Contract with the Georgia Department of Transportation.
|
Library
|
Complete
|
$5,000,000
|
|
10/16/1999
|
Cultural
|
1993-1998
|
Design, construct and equip an addition and renovation of the main library. (2002 Bull St)
|
|
The Live Oak Library Board (previously the Chatham-Effingham-Liberty Regional Library Board) managed the project. Chatham County funded $5 million of the project with the balance from funding from the State of Georgia.
|
Lucas Theatre
|
Complete
|
$1,700,000
|
$-
|
09/16/2003
|
Cultural
|
1993-1998
|
Provide funding through contract for renovation of historic theater (32 Abercorn St).
|
See also 1998-2003 SPLOST
|
Public funds matched private contributions to complete the project. With the 1993-1998 SPLOST, the 1998-2003 SPLOST and federal and city funding, public funds contributed about 25% of the project`s cost.
|
May Street YMCA
|
Complete
|
$1,178,535
|
|
08/16/1999
|
Recreation
|
1993-1998
|
Design, construct and equip renovation and addition to the YMCA at 1110 May Street in Savannah.
|
|
The YMCA conveyed ownership of the property to Chatham County as a safeguard to protect public interest in the project. Architect: Gunn, Meyerhoff, Shay Architects Phase I Contractor: Walter Strong Phase II Contractor: C. E. Hall Construction
|
Memorial Stadium
|
Complete
|
$232,142
|
$-
|
|
Recreation
|
1993-1998
|
Renovation of Chatham County-owned stadium. Project included replacement of lighting, field improvements and amenities (i.e. locker rooms).
|
|
Original budget of $95,000 increased w/ interest earnings from SPLOST fund. The 1993-1998 SPLOST included provision that interest earnings could be used to fund projects (eligible under state law) from the County`s 5-Year CIP.
|
Mighty 8th Heritage Museum: DCA Grant
|
Complete
|
$350,000
|
|
12/12/2002
|
Cultural
|
1993-1998
|
Funds provided by grant from the Georgia Department of Community Affairs, assisted in expanding the museum's exhibit program. (Bourne Ave - Pooler)
|
Chatham County contracted with Mighty 8th to ensure proper expenditure of funds in accordance with state's requirements.
|
Though not SPLOST funded, the project became included because the State of Georgia opted to include grant with funding designated for the Trade Center (a 1993-1998 SPLOST-funded project).
|
Montgomery Cross Road/Middleground Rd. Phase 1 Perimeter Rd. Relocation
|
Complete
|
|
$787,000
|
|
Roads
|
1993-1998
|
To relocate a portion of the two lane Perimeter Road on Hunter Army Airfield to provide right-of-way for construction of Montgomery Cross Road/Middleground Road.
|
|
|
Mother Mathilda Beasley Park--Phase 1 & 2
|
Complete
|
$835,552
|
$-
|
06/16/2000
|
Recreation
|
1993-1998
|
Project included acquisition of property (Phase I) and master plan for development and design and construction of improvements (demolition, site preparation) for ballfields, asphalt perimeter trail, playground equipment and landscaping (Phase 2).
|
Phase I funded through 1993-1998 SPLOST. Phase II, funded through the 1995 referendum, provided additional funds. Phase III, including expansion of site by acquisition/gift of adjoining property, will be funded through 2003-2008 SPLOST.
|
Previously known as East Broad Park. Ph 1: 1993-1998 SPLOST ($483,000), Ph 2: 1995 SPLOST ($250,000), Ph 3: 2003-2008 SPLOST
|
No Wake Project
|
Complete
|
$158,085
|
|
09/16/1998
|
Recreation
|
1993-1998
|
Construct and install "No Wake" signs on designated coastal waterways approved by Georgia Department of Natural Resources.
|
|
Approved funding of $48,000. Additional funding for this recreational project became funded through interest earnings from SPLOST fund.
|
Ogeechee Farms Drainage - Phase 1
|
Complete
|
$310,000
|
$-
|
03/31/2005
|
Drainage
|
1993-1998
|
Construct storm water drainage improvements and provide access for maintenance between Waynesboro and Chevis Roads.
|
|
Project extends from Chevis Road to downstream of Waynesboro Road. Features include closing in drainage ditch with drainage pipe and larger culverts under roadways.
|
Olympic Pool
|
Complete
|
$4,737,285
|
$-
|
05/16/1998
|
Recreation
|
1993-1998
|
Design, construct and equip competitive (50 meter) pool and amenities (locker room) for use in training and competition. (on Sallie Mood Dr.)
|
|
1993-1998 SPLOST funded $2.5 million; 1995 vote added $2 million to the project. Additional funding for this recreational project became funded through interest earnings from SPLOST fund.
|
Parking Lot/Recreational Complex
|
Complete
|
$176,479
|
|
06/16/1999
|
Recreation
|
1993-1998
|
Add parking to meet needs of expanded facilities within the Bacon Park Recreational Complex, especially for regional events at the Aquatic Center and Soccer Complex. Fields also serve parking needs of Ambuc Park and Guy Minick Complex. (Saliie Mood Dr.)
|
|
Parking lots designed by County Dept. of Engineering. Surface material installed as crush and run for cost and to avoid need for drainage retention.
|
Parking Lot: Aquatic Center/Soccer Complex
|
Complete
|
$112,132
|
$-
|
06/16/1999
|
Recreation
|
1993-1998
|
Add parking to meet needs of expanded facilities within the Bacon Park Recreational Complex, especially for regional events at the Aquatic Center and Soccer Complex. Fields also serve parking needs of Ambuc Park and Guy Minick Complex. (Sallie Mood Dr.)
|
|
Parking lots designed by County Dept. of Engineering. Crushed stone surface material installed for cost saving & to avoid need for drainage retention. This recreational project became funded through interest earnings from the SPLOST fund.
|
Parks Renovation Fund
|
Complete
|
$90,000
|
|
|
Recreation
|
1993-1998
|
Funding for capital outlay improvements at older regional parks, including Lake Mayer on Montgomery Cross Road and Stell Park on Bush Road.
|
|
The 1993-1998 SPLOST included a provision that interest earnings could be used to fund projects (eligible under state law) from the County's 5-Year CIP. This project became funded through interest earnings from SPLOST fund.
|
Pennsylvania Ave. (Eastside) Community Center
|
Complete
|
$581,560
|
$-
|
06/25/1998
|
Cultural
|
1993-1998
|
Design, construct and equip a 4,000 SF community center to be used for senior citizen services, community meetings and city programs. The project included 600 SF addition to the Shuman Middle School gym for a weight-lifting center(415 Goebel Ave).
|
|
The project was a design/build partnership with an architect and builder. The project was built on the campus of Shuman Middle School. Architect: Bazemore, Mastrianni Wilson & Associates, Inc. Contractor: Pioneer Construction, Inc.
|
Pooler Pkwy. from Pine Barren Rd. to S.R. 26/U.S. 80
|
Complete
|
$1,449,194
|
$7,000,000
|
|
Roads
|
1993-1998
|
Construction of a new four lane divided road from Pine Barren Road to S.R. 26/U.S. 80, including a new interchange at S.R. 26/U.S. 80.
|
|
Chatham County paid for the design and purchased the right-of-way for this project. GDOT paid for the construction.
|
Bandshell Project
|
Complete
|
$787,500
|
$-
|
|
Cultural
|
1993-1998
|
Funding to provide outdoor bandshell, including sheltered sphere and event-related amenities for performers, for cultural events.
|
"Complete" means Chatham County issued check to City of Savannah to complete the project. Refer to City of Savannah for project status.
|
Chatham County provided funds to the City of Savannah to complete the project. Completed: 1998
|
Bandshell (Portable)
|
Complete
|
$218,416
|
|
|
Cultural
|
1993-1998
|
Acquire two portable bandshells to accommodate stage, lighting and sound needs for outdoor events.
|
The popularity of the portable bandshells can be confirmed by their constant use, especially for weekend community events, by cultural, civic and community groups.
|
|
Bandshell (Trade Center)
|
Complete
|
$-
|
$-
|
|
Cultural
|
1993-1998
|
Project was incorporated into riverfront design of outdoor stage as part of the Trade Center esplanade. With renewed interest in separate, outdoor pavilion, bandshell project separated with new funding (interest earnings from Trade Center)
|
|
See "Bandshell Project" Completed: 1995
|
Battlefield Park
|
Complete
|
$915,000
|
|
|
Cultural
|
1993-1998
|
Funded part of Battlefield Park project, including master plan and contribution toward City of Savannah's acquisition of property. Part of Roundhouse Complex.
|
"Complete" means Chatham County completed its obligation under SPLOST by providing funds to the City of Savannah.
|
Consistent with the SPLOST resolution and agreement prior to the referendum, Chatham County issued checks to the City of Savannah for the project. Completed: 1998
|
Beach Project
|
Complete
|
$494,980
|
|
|
Recreation
|
1993-1998
|
Funds helped to provide match for Tybee Island to secure federal and state grants for beach renourishment.
|
Chatham County provided funds to City of Tybee Island on a reimbursement basis.
|
Per SPLOST resolution and intergovernmental agreement, Chatham County funded Tybee Island for engineering study and design and construction of dune walkovers and vegetation.
|
Bond Ave., Heather St., Betran St., Shore Ave.
|
Complete
|
$-
|
$-
|
|
Roads
|
1993-1998
|
Paving and drainage of dirt roads.
|
Projects are complete.
|
|
Bonny Bridge Intersection Improvements
|
Complete
|
$2,564,370
|
|
|
Roads
|
1993-1998
|
Intersection improvement on State Route 21.
|
|
|
Central Ave. (East), Smith Dr., Cherokee Ave., Saussy Ave.
|
Complete
|
$642,551
|
|
|
Roads
|
1993-1998
|
Paving and drainage of 4 - 2 lane County dirt roads.
|
|
|
Charles Brooks Park (Renovation Program)
|
Complete
|
$84,810
|
$-
|
06/30/2004
|
Recreation
|
1993-1998
|
Capital outlay funds for renovating ballfields, scoreboard and sports building (Concord Rd.).
|
|
The 1993-1998 SPLOST resolution included a provision that interest earnings could be used to fund projects (eligible under state law) from the County 5-Year CIP. This recreational project became funded through interest earnings from SPLOST fund.
|
Jimmy DeLoach Pkwy., Phase II
|
Construction
|
$465,642
|
|
|
Roads
|
1993-1998
|
Extension of the Jimmy DeLoach Parkway from S.R. 26/U.S. 80 to I-16 (a four lane limited access road with a grassed median).
|
Project is under construction by GDOT.
|
Chatham County is paying for the design of this project and for the right-of-way. The GDOT will pay for the construction costs with federal and state funds.
|
S.R. 204 Intersection at Henderson Blvd.
|
Cancelled
|
$-
|
$-
|
|
Roads
|
1993-1998
|
Project was proposed to add an intersection to relieve congestion at the entrance to Gateway Savannah near I-95. The GDOT would not support the project. No funds were spent and none are budgeted.
|
|
|
S.R. 30 Intersection Improvements on S.R. 25
|
Complete
|
$-
|
|
|
Roads
|
1993-1998
|
Scope has not been established.
|
|
No funds are budgeted.
|
Civil Rights Museum--Phase 1, 2
|
Complete
|
$2,447,080
|
|
01/07/1997
|
Cultural
|
1993-1998
|
Phase 1 included acquisition of property, design and construction/renovation of the Museum, which focuses on the Civil Rights Movement in Savannah. Phase 2 included the exhibit program, funded through the 1995 SPLOST.
|
Addition planned as part of 2003-2008 SPLOST.
|
Besides $1 million funded through the 1993-1998 SPLOST, voters approved $750,000 in a 1995 SPLOST vote for the exhibit program. Other funding came from the Civil Rights Museum Board of Directors and through interest earnings. (460 MLK Jr. Blvd)
|
White Bluff/Coffee Bluff Extension
|
Complete
|
$212,947
|
|
|
Roads
|
1993-1998
|
|
On hold.
|
|
Community Centers Furniture & Fixtures
|
Complete
|
$37,178
|
$-
|
|
Cultural
|
1993-1998
|
Provided funds for furniture, fixtures and equipment for various community center projects funded by SPLOST 1993-1998 funds.
|
Currently operating: Pennsylvania (School Board), Hudson Hill (City of Savannah), Woodville (City of Savannah) and Whitemarsh Island (Chatham County)
|
Funding approved in 1995 SPLOST. Completed: 1998. Community projects included: Pennsylvania Community Center, Hudson Hill Community Center, Woodville Community Center and Whitemarsh Island Community Center
|
Diamond Causeway Widening
|
Complete
|
$389,699
|
$-
|
|
Roads
|
1993-1998
|
Widen the Diamond Causeway between Skidaway Narrows bridge and McWhorter Dr.
|
Project is complete.
|
|
Dolan Dr.
|
Complete
|
$378,240
|
|
10/12/2000
|
Roads
|
1993-1998
|
Paving and drainage for a two lane dirt road, including improvement of the drainage outfall.
|
|
This road was on the County's dirt road paving list. The area had some existing storm drainage problems in the downstream system so additional enlarged piping was added to the project to relieve this problem.
|
Fawcett Canal - Phase 1
|
Complete
|
$1,102,691
|
$-
|
12/31/2002
|
Drainage
|
1993-1998
|
Widen canal and increase the size of culvert crossings at roadways from lagoon at Dovetail Crossing to tidegate at Grove Point Rd.
|
|
|
Frank Callen Boys & Girls Club
|
Complete
|
$700,000
|
$-
|
|
Recreation
|
1993-1998
|
Provided funds for expansion and renovation of facilities for recreational non-profit organization (Charlton Street).
|
|
Per SPLOST resolution and intergovernmental agreement, Chatham County accepted ownership of the property during project + five years to maintain public`s interest in expenditure of public funds. SPLOST 1993-1998= $450,000; SPLOST 1995=$250,000.
|
Golden Isles Drainage - Phase 1
|
Complete
|
$100,000
|
$-
|
06/15/2001
|
Drainage
|
1993-1998
|
Improve channel and increase size of storm pipes from Tropical Way north to Blue Heron Dr.
|
|
|
Grove Point Rd. Canal Crossing
|
Complete
|
$340,584
|
$-
|
06/15/2007
|
Drainage
|
1993-1998
|
Increase size of culvert crossing at Grove Point Road.
|
|
|
Gulfstream Entrance Area
|
Complete
|
$50,125
|
$-
|
12/12/1996
|
Roads
|
1993-1998
|
Add left turn for Gulfstream entrance road.
|
|
|
Hudson Hill Community Center
|
Complete
|
$256,970
|
$-
|
05/16/1996
|
Cultural
|
1993-1998
|
Provide funding to design, construct and equip a 4,000-square foot community center for community meetings, city programs, and private affairs. (2231 Hudson Street)
|
Operated by the City of Savannah
|
Architect: G. B. Design Associates. Engineer: Freeman & Vaughn Engineering
|
Truman Pkwy., Phase 5 (Sales Tax 1)
|
Complete
|
$9,833,237
|
|
|
Roads
|
1985-1993
|
Extension of the Harry S. Truman Parkway (four lane divided limited access road) from Whitefield Ave. to Abercorn St.. Includes bridge over the Vernon River and at-grade intersections at Abercorn St.
|
|
Chatham County paid for the design of this project and acquired the right-of-way. The construction cost will be paid for with federal and state funds.
|
TSM on Abercorn St. from DeRenne Ave. to Victory Dr.
|
Complete
|
$200,000
|
|
|
Roads
|
1985-1993
|
Intersection improvements at various intersections between DeRenne Ave. and Victory Drive. (TSM = Traffic System Management)
|
|
|
TSM on Waters Ave. from Stephenson Ave. to Wheaton St.
|
Complete
|
$3,308,866
|
|
|
Roads
|
1985-1993
|
Intersection improvements on Waters Ave. between Stephenson Ave. and Wheaton St. (TSM = Traffic System Management)
|
|
|
U.S.17 North at Brampton Rd. at the Old Traffic Circle
|
Complete
|
$736,216
|
|
|
Roads
|
1985-1993
|
Construction of a new interchange at the location of the old traffic circle.
|
|
|
Veterans Pkwy. from S.R. 204 to I-516 (Lynes Pkwy.)
|
Complete
|
$29,085,964
|
$14,685,000
|
04/29/1998
|
Roads
|
1985-1993
|
A four lane divided highway on new location including bridges over the Little Ogeechee River, Buckhalter Rd. overpass, interchange and bridges at Lynes Parkway. Originally called Southwest Bypass.
|
|
|
Waters Ave. from Montgomery Cross Road to Stephenson Ave.
|
Complete
|
$2,887,972
|
$3,190,288
|
08/31/1994
|
Roads
|
1985-1993
|
Intersection improvements
|
|
|
Wheaton St. Widening from Liberty St. to Bee Rd.
|
Complete
|
$4,419,851
|
$-
|
01/24/2002
|
Roads
|
1985-1993
|
Widen Wheaton St. including intersection improvements between Liberty St. and Bee Rd.
|
|
|
White Bluff Rd. from Abercorn St. to DeRenne Ave.
|
Complete
|
$1,150,752
|
$2,700,000
|
11/25/1987
|
Roads
|
1985-1993
|
Widening of the road from two lanes to four lanes with a divided median.
|
|
This project was initially delayed by the Savannah Tree Foundation because of their strong objection to the original plan design to cut down live oak trees.
|
White Bluff Rd. from Montgomery Cross Road to Windsor Rd.
|
Complete
|
$5,501,660
|
$2,095,000
|
03/17/1992
|
Roads
|
1985-1993
|
Widening from two lanes to four lanes.
|
|
|
Whitemarsh Island Road
|
Complete
|
$479,292
|
|
|
Roads
|
1985-1993
|
Construction of new two lane road from U.S. 80 to Johnny Mercer Boulevard
|
|
|
Abercorn Safety Projects
|
Complete
|
$558,540
|
$-
|
12/31/2009
|
Roads
|
1993-1998
|
Intersection improvements on Abercorn Street: at Tibet Ave., Oglethorpe Mall, DeRenne Ave., Apache Ave. & Largo Dr..
|
|
County agreed to purchase the right-of-way with GDOT funds, to pay for any reimbursible utility relocations and the design. GDOT paid for the construction costs (est. $2,484,000).
|
Administrative Annex/Police Headquarters
|
Complete
|
$5,442,539
|
$-
|
01/28/1998
|
Other
|
1993-1998
|
Design, construct and equip 24,000 square foot building for Chatham County Police Department (relocated from Hodgson Memorial Drive) and satellite citizen service centers for Chatham County Department of Building Safety & Regulatory Services.
|
With creation of the Savannah-Chatham Metropolitan Police Department in 2003, location began to serve merged police services, including 911 Center.
|
Project constructed on property acquired in 1993 to relocate Police Dept, Juvenile Court and Georgia Regional Youth Detention Center. The facilities are on Police Memorial Dr.
|
Anderson-Cohen Weightlifting Center
|
Complete
|
$397,258
|
|
02/01/1997
|
Recreation
|
1993-1998
|
Design, construct and equip 8,000 SF weightlifting center in concert with Team Savannah, a non-profit organization that trains Olympic weightlifters and provides strength training for the public and special needs students. Located on Varnedoe Dr.
|
Contracted to Team Savannah for management and operations.
|
1993-1998 SPLOST funded Phase I at $200,000 with $98,000 added through 1995 referendum. Balance of project funded through interest earnings from SPLOST fund in accordance with resolution and intergovernmental agreement.
|
Bamboo Farm & Coastal Gardens
|
Complete
|
$204,803
|
|
06/26/2002
|
Roads
|
1993-1998
|
Paving and drainage for two lane dirt road and parking areas at the Bamboo Farm and Coastal Gardens.
|
Project is complete.
|
|
S.R. 21 from I-95 to County line
|
Complete
|
$41,911
|
|
|
Roads
|
1985-1993
|
Widening from two lanes to four lanes including bridges.
|
|
|
S.R. 25/U.S. 17 at S.R. 204/Abercorn St. Intersection Improvements
|
Complete
|
$205,554
|
$-
|
|
Roads
|
1985-1993
|
Intersection upgrade to improve level of service.
|
|
|
S.R. 25/U.S. 17 at the Burkhalter Rd. Intersection
|
Complete
|
$19,100
|
|
|
Roads
|
1985-1993
|
Intersection improvements for safety and level of service.
|
|
|
S.R. 25/U.S. 17 Enhancement from the Florida line to South Carolina line
|
Complete
|
$7,995
|
|
|
Roads
|
1985-1993
|
|
|
|
S.R. 25/U.S. 17 from Dean Forest Rd. to Lynes Pkwy.
|
Complete
|
$5,686,022
|
$4,341,000
|
06/16/1995
|
Roads
|
1985-1993
|
Widening of S.R. 25/U.S. 17 from Dean Forest Rd. to I-516 (Lynes Parkway) from a two lane road to four lanes divided including new bridges over the railroad.
|
|
|
S.R. 25/U.S. 17 from S.R.204 (Abercorn St.) to S.R. 307 (Dean Forest Rd.)
|
Complete
|
$1,295,168
|
|
|
Roads
|
1985-1993
|
The widening of S.R. 25/U.S. 17 from S.R. 204 (Abercorn St.) to S.R. 307 (Dean Forest Rd.) from two lanes to four lanes including the construction of new bridges at creek crossings.
|
|
Chatham County purchased the right-of-way on this project using GDOT funds. The administrative costs associated with the right-of-way purchases was paid for by Chatham County. The construction cost are being paid for with federal and state funds.
|
S.R. 25/U.S. 17 from the Ogeechee River to S.R. 204/Abercorn St.
|
Complete
|
$1,739,000
|
$-
|
|
Roads
|
1985-1993
|
Widening of U.S. 17 from the Ogeechee River to S.R. 204 from two lanes to four lanes. Constructed by the GDOT.
|
|
Chatham County purchased the right-of-way for this project using GDOT funds. The administrative costs associated with the right-of-way purchases were paid for by the County. The construction cost was paid for with federal and state funds.
|
S.R. 25/U.S. 17 Georgia Port Authority Entrance
|
Complete
|
$30
|
|
|
Roads
|
1985-1993
|
Improvements to the entrance of the Port Authority.
|
|
|
S.R. 26/U.S. 80 from Bloomingdale to the Effingham Co. Line
|
Complete
|
$154,287
|
|
|
Roads
|
1985-1993
|
The original project was to widen from 2 lanes to 4 without a median. The R/W was acquired. GDOT took over the project, extended it to SR 17 in Effingham and revised it to a 5 lane section.
|
|
County's participation was for engineering and right-of-way acquisition costs and that is complete. The project was awarded to RB Baker with scheduled completion date of October 2006.
|
S.R. 26/U.S. 80 from Chatham Pkwy. to I-95
|
Complete
|
$2,689,555
|
$3,075,000
|
01/31/1992
|
Roads
|
1985-1993
|
Widening of a two lane road to four lanes, including a new bridge over the railroad.
|
|
|
S.R. 26/U.S. 80 from I-516 to Victory Dr.
|
Complete
|
$655,443
|
|
|
Roads
|
1985-1993
|
Widening of S.R. 26/U.S. 80 from I-516 to Victory Dr. from two lanes to four lanes.
|
GDOT is working on the Environmental Assessment.
|
This is a GDOT project that the County will participate in by purchasing the right-of-way. The GDOT is designing the project and will pay for the construction costs with federal & state funds.
|
S.R. 26/U.S. 80 from S.R. 17 in Bloomingdale and Pooler
|
Complete
|
$1,029,946
|
$1,250,000
|
08/22/1990
|
Roads
|
1985-1993
|
Widening of S.R. 26/U.S. 80 from two to four lanes (creating one-way pair).
|
|
|
S.R. 26/U.S. 80 in Garden City
|
Complete
|
$268,157
|
|
|
Roads
|
1985-1993
|
|
|
|
S.R. 26/U.S. 80 Whitemarsh Island Roadway Median
|
Complete
|
$20,000
|
|
|
Roads
|
1985-1993
|
|
|
|
S.R. 26/U.S.80 Widening from Johnny Mercer Blvd. to Bryan Woods Rd.
|
Complete
|
$57,871
|
$830,000
|
05/06/1988
|
Roads
|
1985-1993
|
Widening of the road from two lanes to four lanes.
|
|
|
S.R. 307 (Dean Forest Rd.) from U.S. 17 to I-16
|
Complete
|
$133
|
$5,000,000
|
|
Roads
|
1985-1993
|
Widening of S.R. 307/Dean Forest Road from two lanes to four lanes from S.R. 25/U.S. 17 to I-16.
|
|
Scheduled construction completion in November 2013.
|
Skidaway Widening at Victory Dr. (Five Points)
|
Complete
|
$1,872,241
|
$1,130,000
|
06/03/1995
|
Roads
|
1985-1993
|
Intersection improvements (left turn lanes and new signals).
|
|
|
Staley Ave. Overpass
|
Complete
|
$3,546,381
|
|
|
Roads
|
1985-1993
|
New bridge
|
|
|
Stephenson Ave. from Abercorn St. to Waters Ave.
|
Complete
|
$6,129,578
|
$-
|
|
Roads
|
1985-1993
|
Intersection improvements and the addition of center turn lane.
|
|
|
Triplett Park Entrance Rd.
|
Complete
|
$254,263
|
|
07/06/2000
|
Roads
|
1985-1993
|
Construction of a two lane entrance road into Tom Triplett Park.
|
|
|
Truman Pkwy., Phase 1
|
Complete
|
$17,191,783
|
$-
|
|
Roads
|
1985-1993
|
A four lane limited access highway on new location from Henry and Anderson streets to President St..
|
|
The list of projects provided by GDOT did not list the Truman Parkway Ph. 1. GDOT paid for the construction cost.
|
Truman Pkwy., Phase 2
|
Complete
|
$10,383,000
|
$26,123,529
|
04/30/1998
|
Roads
|
1985-1993
|
Extension of the Parkway (four lane divided highway) from south of Henry and Anderson Streets to President St.
|
|
|
Truman Pkwy., Phase 3
|
Complete
|
$13,951,856
|
$31,458,000
|
|
Roads
|
1985-1993
|
Extension of the Harry S. Truman Parkway from DeRenne Ave. to Montgomery Cross Road.
|
|
Chatham County paid for the design of this project and purchased the right-of-way. The construction cost was paid for by GDOT with federal and state funds.
|
Truman Pkwy., Phase 4
|
Complete
|
$10,429,948
|
$9,707,000
|
09/01/2005
|
Roads
|
1985-1993
|
Extension of the four lane Harry S. Truman Parkway from Montgomery Cross Road to Whitefield Ave.
|
|
|
Veterans Parkway Improvements 2019
|
Construction
|
$4,000,000
|
$-
|
On Going
|
Roads
|
1985-1993
|
Mill, Inlay, drainage upgrades and minor clearing to reestablish clear zones.
|
Construction underway by Reeves Construction.
|
|
Bourne Ave. Relocation
|
Complete
|
$4,332,608
|
|
12/18/1997
|
Roads
|
1985-1993
|
Reconstruct and realign an existing two lane road.
|
|
|
Bryan Woods Rd. Widening
|
Complete
|
$53,684
|
$567,000
|
09/09/1988
|
Roads
|
1985-1993
|
Widening from two lanes to four lanes between US 80 and Johnny Mercer Blvd.
|
Project is complete.
|
|
Canebrake Road Improvement Project
|
Complete
|
$2,747,679
|
$-
|
Complete
|
Roads
|
1985-1993
|
Project constructed a new 10-ft trail and a 5-ft sidewalk along Canebrake Road between State Route 204 and Basin Road.
|
Project is complete.
|
|
Chatham Pkwy. (Garrard Ave. to SR 25/US 17)
|
Complete
|
$3,659,714
|
$-
|
04/29/1998
|
Roads
|
1985-1993
|
Construct four lane divided road on new location, including two bridges crossing Veterans Parkway.
|
Project is complete.
|
|
Chatham Pkwy. (SR 25/US 17 to SR 26/US 80)
|
Complete
|
$3,445,334
|
$-
|
|
Roads
|
1985-1993
|
Widen Chatham Parkway from two lanes to four lanes.
|
Project is complete.
|
|
Crossroads Pkwy.
|
Complete
|
$2,652,823
|
$-
|
|
Roads
|
1985-1993
|
Construction of a two lane road on new location through the industrial park.
|
|
|
Gulfstream Rd. at S.R. 21
|
Complete
|
$131,349
|
$52,410
|
|
Roads
|
1985-1993
|
Extension of a dedicated right turn from Gulfstream Road onto S.R. 21.
|
|
|
Henderson Boulevard
|
Complete
|
$916,292
|
$-
|
04/01/1995
|
Roads
|
1985-1993
|
Constructed a 2 lane road from Gateway Blvd to the Henderson Golf Club entrance road.
|
|
|
Henderson Boulevard, Phase 2
|
Complete
|
$285,275
|
$-
|
04/01/1996
|
Roads
|
1985-1993
|
Constructed a 2 lane street from the Henderson Golf Club entrance to Little Neck Road.
|
|
The County paid 25% of the construction cost with the Henderson Golf Community developer paying 75% and donating the right-of-way
|
Interchange at S.R. 25/U.S. 80
|
Complete
|
$11,373,236
|
$-
|
07/01/1996
|
Roads
|
1985-1993
|
Construction of a new fly-over interchange on Islands Expressway at U.S. 80.
|
|
|
Interchange at Veterans Pkwy. & S.R. 204/Abercorn
|
Complete
|
$7,362
|
$29,541,862
|
11/30/2003
|
Roads
|
1985-1993
|
A new four lane looped bridge flyover interchange on S.R. 204 at Veterans Parkway.
|
|
|
Interchange on I-95 at Airport
|
Complete
|
$2,551
|
$7,014,000
|
06/07/1999
|
Roads
|
1985-1993
|
New diamond interchange at the airport connector road that connects to Pooler Parkway. Constructed by GDOT.
|
Project is complete.
|
|
Jimmy DeLoach Pkwy. at I-95
|
Complete
|
$160,074
|
$11,681,000
|
|
Roads
|
1985-1993
|
New Interchange at I-95, including a bridge over I-95 and the connecting ramps.
|
|
|
Jimmy DeLoach Pkwy. from S.R. 26/U.S.80 to South of S.R. 21
|
Complete
|
$17,706,114
|
$-
|
12/11/1997
|
Roads
|
1985-1993
|
A four lane divided road on new location including 4 bridges over the Norfolk Southern Railroad and CSX Railroad, beginning at U.S. 80 and extending to 0.28+/- miles east of CSX Railroad.
|
|
|
Johnny Mercer Blvd. from Bryan Woods Rd. to S.R. 26/U.S. 80
|
Complete
|
$1,599,066
|
$704,000
|
11/21/1996
|
Roads
|
1985-1993
|
Widening of the road from two lanes to four lanes with a divided median.
|
|
|
Johnny Mercer Blvd. from Bryan Woods Rd. to Sapelo Rd.
|
Complete
|
$480,641
|
$4,460,000
|
09/24/1991
|
Roads
|
1985-1993
|
Widening of the road from two lanes to four lanes with a median including a new four lane bridge over Turners Creek.
|
|
|
Montgomery Cross Road from Abercorn St. to Skidaway Rd.
|
Complete
|
$8,159,670
|
$3,249,000
|
11/21/1996
|
Roads
|
1985-1993
|
The widening of Montgomery Cross Road from two lanes to four lanes, including bridges across Hayners Creek.
|
|
|
Pooler Bypass from U.S. 80 to I-95
|
Complete
|
$5,237,787
|
$-
|
04/01/1997
|
Roads
|
1985-1993
|
Construct new four lane road from U.S. 80 to I-95.
|
|
Now known as the Pooler Parkway
|
President St. from Randolph St. to S.R. 26/U.S. 80
|
Complete
|
$1,236,334
|
$4,710,000
|
08/22/1990
|
Roads
|
1985-1993
|
Widening of the road from two lanes to four lanes.
|
|
|
Richardson Creek Bridge
|
Complete
|
$5,100
|
$260,000
|
06/08/1987
|
Roads
|
1985-1993
|
Bridge replacement over Richardson Creek.
|
|
|
Robert McCorkle Bike Trail
|
Complete
|
$327,435
|
|
09/27/2001
|
Recreation
|
1985-1993
|
Extension of the Robert McCorkle Bike Trail on Wilmington Island.
|
Original Project is complete. Funds identified to upgrade portions of the existing trail. Final bid package preparation underway.
|
|
Various County Roads
|
On Going
|
$59,903,020
|
|
|
Roads
|
1985-1993
|
Design and paving costs for 119 small dirt road and reconstruction projects.
|
Projects are in various stages of design and construction. The majority have been completed. County costs shown are expended to date.
|
|
Bay St. Viaduct
|
Complete
|
$886,674
|
$10,044,000
|
06/19/1995
|
Roads
|
1985-1993
|
Construct new four lane bridge over the Central of Georgia railroad on S.R. 26/U.S. 80 including new signals at the intersections.
|
|
|
Eli Whitney Blvd.
|
Complete
|
$1,186
|
$-
|
|
Roads
|
1985-1993
|
Preliminary survey work for a planned extension of Eli Whitney Boulevard. The planned enlargement of the industrial park did not come to fruition. The project was never done
|
|
|
Area Beautification
|
Complete
|
$517,435
|
$-
|
|
Roads
|
1985-1993
|
Landscaping on roadways for the Olympics (US 80, SR 21, Gateways to Savannah area)
|
|
|
McCorkle Bike Trail Improvements
|
Design
|
$1,000,000
|
$-
|
On Going
|
Roads
|
1985-1993
|
Project will upgrade the existing, deteriorated portions of McCorkle Bike trail.
|
Staff needs to develop bid documents for the project.
|
|
Airport Road & Bridge
|
Complete
|
$385,193
|
$2,244,955
|
09/01/1996
|
Roads
|
1985-1993
|
Construct 3.4 miles of road for airport extending to Jimmy DeLoach Parkway (named Airport Connector Rd).
|
|
|
Administrative Annex Entry Rd.
|
Complete
|
$407,774
|
$-
|
|
Roads
|
1985-1993
|
Construct road from Chatham Parkway to County Police Headquarters (Police Memorial Dr)
|
|
|